    Hi All,

    In my P6 schedule, a few task dependent critical activities have negative float while I have no constraint in my schedule (except for some soft constraints of "As late as possible"). Nor have my schedule a must finish by constraint. When I checked the baseline, all these floats were Zero and seems that this weird happened after the recent update. Can anyone help me what to do and what is the reason for this?
     
  2. zargon

    zargon Community Moderator Forum Guru

    Messages:
    2,351
    Likes Received:
    348
    Trophy Points:
    1,430
    Location:
    Aurora, CO
    What are you talking about? Your post is confusing, at best.