How to change the PO "need by date" in "recommendations"

Discussion in 'Oracle SCM & Manufacturing' started by AndreasFilipsson, Jan 16, 2014.

  1. Hi,
    I want to change the recommended need by date that is generated in ASCP module, in the recommendations/Purchase orders
    I assume it must be possible to change this date? Now the fields are only grey and not possible to change..
     
  2. P D Sharma

    P D Sharma Active Member

    Messages:
    7
    Likes Received:
    0
    Trophy Points:
    55
    You can change Tolerance in Receiving Controls Early Days or Days Late as per your requirement